Seattle’s Sound Transit Is Officially Insane

Mariya Frost, of the Washington Policy Center, has alerted me that Seattle should be added to the list of cities with transit projects gone wild. Sound Transit, the region’s rail transit authority, has raised the projected costs of projects built between 2017 and 2046 from $54 billion to $142 billion.

An artist’s impression of a planned Seattle light-rail line. Notice that the artist didn’t project any decline in automobiles or driving. Photo from Siemens.

Most of the increase is for the cost of building 62 miles of light-rail lines. Seattle already had the most-expensive light-rail system in the nation, but the latest costs are completely insane. Continue reading

Transit Construction Costs Run Wild

America’s transit industry has been heavily criticized for spending so much on construction. Yet the industry continues to roll up cost overrun after cost overrun for projects that should have been too expensive to build in the first place.

VTA’s planned single-bore tunnel into downtown San Jose. Figure by VTA.

Take, for example, the BART line to San Jose, which is being planned and built by the Santa Clara Valley Transportation Authority (VTA), which has never displayed much competence in the past. Rather than cut and cover two small tunnels into downtown San Jose, which is the usual practice, VTA wants to bore one gigantic tunnel three to four stories underground. The 6-mile line was originally projected to cost $4.1 billion, but last October the Federal Transit Administration (FTA) announced that it expected the cost to be $9.1 billion, or $1.5 billion a mile, and the agency expressed doubts that VTA had the funds to cover this cost overrun. Continue reading

LA Metro Celebrates Losing 138 Million Bus Riders

Los Angeles Metro recently celebrated the tenth anniversary of the opening of its Expo light-rail line. Construction on the line began in 2006, a year in which LA Metro buses carried 409 million trips, and the line opened in April, 2012.

The LA Expo line shortly after it opened. Photo by Gary Leonard for Los Angeles Metro.

To help pay for the Expo and other new light-rail lines, LA Metro cut bus service by nearly a quarter between 2006 and 2019. This contributed to the loss of a third of its bus riders, or nearly 138 million trips per year. The Expo line, meanwhile, boosted light-rail ridership by about 2 million annual trips, enough to make up 1.5 percent of the loss in bus ridership. Continue reading

70% of Seattle Light-Rail Riders Don’t Pay

Sound Transit, Seattle’s light-rail agency, has a goal of collecting enough fares to cover 40 percent of operating costs, yet it is collecting just 5 percent. That’s partly because of COVID-depressed ridership, but mainly because the agency makes almost no effort to collect fares. As a result, the agency estimates that 70 percent of its passengers are riding without paying.

Not getting much use: a Sound Transit ticket machine. Photo by Evan Didier.

Like other light-rail systems, Seattle’s operates on an “honor system,” meaning people are expected to pay before they board, but there are no turnstiles to keep them from boarding if they don’t pay. Like other light-rail systems, Seattle’s used to have “fare inspectors” who would hand out tickets to people who didn’t have proof of payment. But then someone pointed out that minorities were getting most of the tickets (maybe because they were most likely to not pay?), so this was deemed inequitable. Continue reading

Lie Rail Supporters Keep On Lying

The Antiplanner has previously written that light rail should be called lie rail because everything its advocates say about it is a lie. The latest proof comes from Capital Metro, Austin’s transit agency, which now admits that light-rail projects voters approved in 2020 are going to cost at least 78 percent more than originally projected.

Capital Metro persuaded voters to support light rail by claiming it would reduce congestion when in fact it will make it worse by taking lanes away from autos and dedicating them to empty tracks carrying empty light-rail trains.

The original projection, of course, was one of many lies told about the project. Almost every light-rail project ever built has cost far more than the original projections, overruns so systematic that Oxford researcher Bent Flyvbjerg says they are “best explained by strategic misrepresentation, that is, lying.” Other lies included overestimated ridership numbers and the claim that light rail is “high-capacity transit.” Continue reading

A New Level of Transit Incompetence

It seems like we are getting more lessons about massive cost overruns for transit projects every couple of weeks. Last week, the Federal Transit Administration issued a “scathing report claiming that the Santa Clara Valley Transportation Authority (VTA) was being “overly optimistic” and “misleading” in its estimates of the costs of building a BART subway to San Jose.

Despite objections from critics, VTA decided to bore an 86-foot deep, 48-foot diameter tunnel rather than build two shallower and smaller tunnels using the cut-and-cover method, which would have been less expensive and saved passengers’ time.

The six-mile-long project was originally estimated to cost $5.6 billion (which is itself ridiculous) and be done in 2029, but the FTA now predicts it will cost as much as $9.1 billion and won’t be complete until 2034. This is $1.5 billion a mile for a transit line that is expected to carry so few riders that early estimates predicted it would cost more than $100 for each new transit rider carried. VTA’s response doesn’t refute anything the FTA said, but basically said it is too late to fix the problems so taxpayers would have to live with them (and pay for them). Continue reading

Purple Line’s Costs Up 98%, Delayed 4 More Years

Maryland’s Purple Line is now expected to cost more than $3.9 billion to construct, up from under $2.0 billion at the time the line was approved, according to a report from the Maryland Department of Transportation. The $3.9 billion includes a $250 million settlement with previous contractors and $219 million spent by the state on the project after the previous contractor quit. The opening date has also been pushed back to fall, 2026, compared with the original date of mid-2020 and the most-recent date of late 2022.

Maryland Governor Larry Hogan and then-Secretary of Transportation Peter Rahn have a laugh at the expense of the taxpayers when they announced that the state would build a “cost-effective and streamlined version of the Purple Line” in 2015. Memo to Gov. Hogan: Light rail is never cost-effective especially when it is predicted to make congestion worse. Photo by Purple Line Transit Constructors.

Like Honolulu’s rail line, the Purple Line is a project that should never have been approved. Even the Federal Transit Administration said it was not worth building until the state fabricated new, ridiculously high ridership estimates. Now that construction has begun, state officials intend to throw good money after bad no matter what the cost. Continue reading

St. Louis MetroWaste

The infrastructure bill was supposed to repair worn out and crumbling infrastructure, but now that it has passed local officials all over the country are eagerly looking forward to spending that money on new projects they won’t be able to afford to maintain. Case in point: St. Louis Mayor Tishaura Jones, who thinks some of those federal dollars should go to building a new light-rail line in the Gateway City.

Light rail in St. Louis operates mostly in an exclusive right of way, which makes it more costly to build but doesn’t add many new riders: MetroLink carried 11 percent fewer riders in 2019 than before it opened its first light-rail line. Photo by Loco Steve.

While admittedly I would be hard pressed to find any light-rail lines that have been successful, St. Louis’ transit system, known as MetroLink, is one of the more unsuccessful. Bus and light-rail ridership had dropped by 25 percent between 2014 and 2019. As of September, it was barely carrying 50 percent of 2019 levels, and given the large numbers of people who plan to keep working at home, it doesn’t look like it will ever fully recover. Continue reading

Good Bye, Peter Rogoff

After six contentious years, Peter Rogoff will leave his $379,600 a year job as CEO of Sound Transit, where he oversaw the construction of billions of dollars of light-rail lines that he didn’t believe in. It’s not clear that his departure is entirely voluntary: he apparently told the Sound Transit board that “he did not foresee remaining in his role beyond the end of 2022.” The board responded by not renewing his contract, which expires in May, effectively firing him.

Peter Rogoff speaking about “advanced transportation technologies” (which don’t include light rail) in 2016. Photo by AvgeekJoe.

I liked Rogoff when he was making $180,000 a year as the administrator of the Federal Transit Administration in the early Obama years. In his first year, he made three discoveries:

  1. America’s rail transit systems had a $77 billion maintenance backlog (since increased to more than $100 billion);
  2. America’s rail transit agencies would rather build new rail lines than maintain their existing ones;
  3. In most situations, bus-rapid transit could do everything rail transit could do for a lot less money.

Continue reading

How to Save Taxpayers’ Money

Seattle taxpayers pay some of the highest taxes in the country so that Sound Transit can build $75 billion worth of light-rail and other transit facilities. Some of those taxpayers must have been overjoyed to read a Sound Transit press release saying, “Local taxpayers to save more than $500 million through USDOT financing assistance.”

Those same taxpayers, however, may be wondering: are they going to get that $500 million back in rebates on the taxes they have paid to date? Is Sound Transit going to reduce future taxes to take this savings into account? Or will Sound Transit just throw a big party with an open bar and invite Seattle taxpayers to attend? How about none of the above.

Early this year, Sound Transit admitted that the cost of two planned light-rail lines will be as much as 70 percent more — than originally projected. That’s $6.2 billion. The agency faces a $6.5 billion shortfall in funds, which plans to deal with by delaying completion of several promised light-rail lines to as late as 2041 — 44 years after taxpayers began paying for them. Continue reading