Maryland Governor Larry Hogan announced Thursday that he was cancelling Baltimore’s Red light-rail line while approving suburban Washington’s Purple Line. However, that approval comes with a caveat that could still mean the wasteful transit project will never be built.
The latest cost estimate for the Purple Line is nearly $2.5 billion for a project that, if done with buses, would cost less than 2 percent as much. The Purple Line finance plan calls for the federal government to put up $900 million, the state to immediately add $738 million, and then for the state to borrow another $810 million.
Instead, Governor Hogan says Maryland will contribute only $168 million to the project, and that local governments–meaning, mainly, Montgomery County but also Prince Georges County–will have to come up with the rest. It isn’t clear from press reports whether Hogan is willing to commit Maryland taxpayers to repay $810 million worth of loans, but it is clear that local taxpayers will have to pay at least half a billion dollars more than they were expecting.