The Tide, Norfolk’s light-rail line, has been open to the public for ten years. As noted in this article in the Pilot, it opened 18 months late after a 60 percent cost overrun.
The Tide light rail in downtown Norfolk. Photo by Dean Covey, Virginia Department of Transportation.
The article claims the light-rail line carried its first million rides “five months ahead of original projections,” but that’s a transit agency lie. The original projections estimated that the rail line would carry 10,400 riders per weekday in its opening year. That would be about 1 million riders in less than four months. In fact, it carried less than half that, just 4,900 riders per weekday in its first year, and took eight months to reach 1 million riders. Continue reading